Answer: 4-6 hours Explanation: The actual installation takes about 4 to 6 hours, but the process may be different depending on the city and utility provider |
Kingdom Electric Company |
Answer: Not sure Explanation: It depends on the complexity of the install |
Light It Up Electric |
Answer: 2-4 hours Explanation: Depending on the panel it takes anyou were from quarter 26 hours |
Alltypes electric llc |
|
ProMatcher |
Answer: 4-6 hours Explanation: This is something that doesn't need to be rushed. A panel change-out requires that the wiring in the existing panel be handled carefully so that it is not damaged. you would also want to mark all of the wires to identify where they go and to make sure that they are reinstalled on the correct size breaker. |
Electrical Services Plus LLC |
Answer: 6-8 hours Explanation: Depending on the existing installation, is the service 200 amps or does it require a service upgrade? Is it hard piped as in commercial applications? |
RAC Electrical Services` |
Answer: 6-8 hours Explanation: There are many variables around this but typically can be completed in one day. |
ElectriTech, Inc. |
|
ProMatcher |
Answer: 6-8 hours Explanation: really just depends on the amount of circuits needed to relocate into new panel |
Electrical Services Inc. |
Answer: 4-6 hours Explanation: all jobs are different so could be longer or shorter |
ELITE ELECTRIC SERVICES |
Answer: Over 8 hours Explanation: You can not use 100 amp wiring on a 200 amp service what do you want to do burn the place down. More information is required is it over head or under ground grid connected |
D B Electric |
|
ProMatcher |
Answer: 4-6 hours Explanation: 4 to 6 hours if we need to replace it in the same location |
Gacem Electric |
Answer: Not sure Explanation: Cannot use existing wiring. Up the panel is upgraded to 200 amp than the meter and feeder wire must also be upgraded. |
Kristoff Electric |
Answer: 4-6 hours Explanation: I always tell people. Their ice won't melt in the freezer. Lol |
Advanced Electrical and Energy |
|
ProMatcher |
Answer: 6-8 hours Explanation: It depends on how many circuits were added through the years, inspections, and the power utility company.(usually 6-8 hours, but that can vary depending on the particular situation) |
LED Electrical Services |
Answer: 6-8 hours Explanation: 2 guys typically most of the day to change panel , meter, and riser. |
DiBiagio Electrical Construction llc |