Answer: 6-8 hours Explanation: Too many factors to accurately say, but typically it will be a full work day. |
G & H Electrical Services, LLC |
Answer: 4-6 hours Explanation: The actual installation takes about 4 to 6 hours, but the process may be different depending on the city and utility provider |
Kingdom Electric Company |
Answer: Not sure Explanation: It depends on the complexity of the install |
Light It Up Electric |
|
ProMatcher |
Answer: 6-8 hours Explanation: Installing a new service and electrical panel usually takes about a day. |
Ross Electric Company |
Answer: 4-6 hours Explanation: This is something that doesn't need to be rushed. A panel change-out requires that the wiring in the existing panel be handled carefully so that it is not damaged. you would also want to mark all of the wires to identify where they go and to make sure that they are reinstalled on the correct size breaker. |
Electrical Services Plus LLC |
Answer: 6-8 hours Explanation: Depending on the existing installation, is the service 200 amps or does it require a service upgrade? Is it hard piped as in commercial applications? |
RAC Electrical Services` |
|
ProMatcher |
Answer: Not sure Explanation: Depends on what needs to be done. |
Aegis Electric LLC |
Answer: 6-8 hours Explanation: really just depends on the amount of circuits needed to relocate into new panel |
Electrical Services Inc. |
Answer: 4-6 hours Explanation: all jobs are different so could be longer or shorter |
ELITE ELECTRIC SERVICES |
|
ProMatcher |
Answer: 2-4 hours Explanation: This requires communication with the power company, inspection department, and electrical contractor working together to ensure the power upgrade is done within code requirements and safety regulations. |
Seabreeze Electric |
Answer: 4-6 hours Explanation: 4 to 6 hours if we need to replace it in the same location |
Gacem Electric |
Answer: Not sure Explanation: Cannot use existing wiring. Up the panel is upgraded to 200 amp than the meter and feeder wire must also be upgraded. |
Kristoff Electric |
|
ProMatcher |
Answer: 6-8 hours Explanation: A service upgrade is an all day job requiring 1 man inside and 1 man outside plus co-ordinating with the power company |
Jove Electric |
Answer: 6-8 hours Explanation: It depends on how many circuits were added through the years, inspections, and the power utility company.(usually 6-8 hours, but that can vary depending on the particular situation) |
LED Electrical Services |
Answer: 6-8 hours Explanation: 2 guys typically most of the day to change panel , meter, and riser. |
DiBiagio Electrical Construction llc |